Construction Schedule


February 2022-Hayden Grove of St. Anthony will begin pre-opening leasing activities in the next three months.  We will locate a sales trailer on site and eventually open a model unit to tour future residents around August 2022.  We expect to have construction completed by December 2022 and residents moving in January 2023.

November 11, 2021-Offsite work and utility work will continue at the property through the third quarter and will finish this month. We were provided tax increment financing for, in part, rerouting utilities on the site and offsite from Minneapolis to St. Anthony. We needed to finish a significant portion of the offsite utilities prior to beginning utility work on the main site because 40+ households relied on the utilities we were rerouting.

Onsite, we have made significant progress with demolition of buildings, mass excavation, utility work, and footings. The main access road from Kenzie was completed in October 2021. 

While the supply chain has been seriously disrupted on a global scale, we have solved all issues that have come up to date and do not have any procurement issues that we know about today. Our construction schedule is currently on pace for a completion in the fourth quarter of 2022.

  1. Proposal Details
  2. City Documents

Development 65 is a developer of senior living in the Twin Cities and intends to complete a senior living facility at 2501 Lowry Ave. The project is a four story, 135-unit senior living facility. Of these 135 senior units, 24 will be memory care, 28 will be assisted living, and 83 independent living.

  1. Steve Grittman

    City Planner

Leasing Inquiries

Hayden Grove Senior Living

612-448-3600

https://haydengroveseniorliving.com/st-anthony-mn/

Project Timeline-Development 65 (Exact dates to be determined)

Document Submitted City Action
PUD Preliminary Development Plan Public Hearing at Planning Commission January 19, 2021 at 7 PM, Planning Commission makes recommendation to City Council on February 9, 2021at 7 PM-City Council approved preliminary stage PUD on February 9, 2021
Final Development Plan City Council meeting April 13, 2021 to consider final stage PUD
Easement Vacation & Dedication